CONSTRUCTION UPDATES

To receive construction updates send an email to info@ctfastrak.com.

Click on the image at right to view larger version of a station construction montage showing linkages along the CTfastrak guideway.

View the new CTfastrak recreational trail access map at Newington Junction Station here. For trail access between the New Britain East Street Station and the cemetery, click here.

New signal crossings are up! View New BritainWest Hartford and Hartford.

View the final Asylum Street lane configuration graphic and Flatbush Avenue ramps wetland mitigation.

  • CONSTRUCTION BULLETIN April 11, 2016 +

    NEWINGTON

    CT fastrak Newington Junction Station - Parking lot construction is scheduled for Tuesday, April 12, to Friday, April 15, 2016 . Work will take place during normal daytime hours, and there are no anticipated disruptions to existing station parking.

    Pedestrian and bus access to the station will not be affected, however the existing turnaround and pedestrian drop-off area will be closed

    Read More
  • CONSTRUCTION BULLETIN March 31, 2016 +

    WEST HARTFORD

    CT fastrak Elmwood Station - Permanent light pole installation at the new parking area is scheduled from Tuesday, April 5, to Friday, April 8, 2016 . Most of the work will take place during the evening and early morning hours, and disruptions to parking will be kept to the minimum possible extent.

    Please note that some parking spaces may be

    Read More
  • CONSTRUCTION BULLETIN December 8, 2015 +

    NEW BRITAIN

    CT fastrak East Main Street Station - Paving operations are scheduled for Thursday, December 10, 2015, between the hours of 9:00 a.m. and 3:00 p.m. Work will take place at the station platforms. Traffic operations on East Main Street will be maintained, but the platforms will be closed to pedestrians.

    Please note that the CT fastrak buses will be

    Read More
  • CONSTRUCTION BULLETIN September 11, 2015 +

    WEST HARTFORD

    Eastbound New Britain Avenue between the Amtrak bridge and South Street - Storm sewer work is scheduled for Monday, September 14, 2015, between the hours of 9:00 am and 3:00 pm. Intermittent lane closures should be expected, however traffic in each direction will be maintained.  View map here .

    The work is being performed as part of the construction of

    Read More
  • CTfastrak Program Announcement - August 4, 2015 +

    Hartford

    A new traffic signal has been installed at the intersection of Park Street and Francis Avenue. This signal has gone into operation as of August 4, 2015 .

    View Signal Location Map Here

    Motorists and pedestrians are advised to be aware of the new signal and to use caution when approaching the intersection.

     



    If you have any questions related

    Read More
  • CONSTRUCTION BULLETIN July 28, 2015 +

    NEW BRITAIN

    Columbus Boulevard at Truman Overpass and the PriceRight shopping plaza - Reconstruction of the PanAm rail crossing and intersection improvements at Robert Loughery Way is scheduled to begin Monday, July 27, 2015. Work is scheduled to last approximately 4 to 5 weeks.

    The work is being performed as part of the construction of CT fastrak .

    One lane of traffic

    Read More
  • Weekly Update: May 29 - June 5, 2015 +

    Take CT fastrak to Saturday's New Britain Memorial Day Parade!
    Route ends near Franklin Square and passes right by the Downtown New Britain Station! For more information click  here
     

    construction wkly update header

    Contractors will be working at all of the new stations to complete final construction items.

     

    Hartford

    • I-84 exit and entry ramps to and from Flatbush Avenue (Exit 45) - Construction
  • Read More
  • Weekly Update: May 22 - May 29, 2015 +

    Take CT fastrak to the Greek Festival this weekend!
    It's a super easy walk to the Greek Festival from the Downtown New Britain Station - for walking directions click  here
     

    construction wkly update header

    Contractors will be working at all of the new stations to complete final construction items.  Nighttime work may be encountered.

     

    Hartford

    • I-84 exit and entry ramps to and from
  • Read More
  • Weekly Update: May 15 - May 22, 2015 +

    Take CT fastrak to the Hartford Wolfpack playoff game tonight!
    Get off at the Bushnell/Asylum Avenue or Travelers @ Main Street stop and walk over to the XL Center. For return travel toward New Britain after the game, the most convenient ‪CT fastrak ‬ stop is in front of Hartford 21 at the corner of Asylum & Trumbull.  Buses run until 12:45

    Read More
  • CONSTRUCTION BULLETIN May 12, 2015 +

    CT rides  Week: use CT fastrak &  try something new!

    For more information on getting involved click   here

    HARTFORD

    Park Street between Pope Park Highway and Sisson Avenue - The nighttime paving work that was originally scheduled for May 11, 2015, has been rescheduled to evenings of Wednesday and Thursday, May 13 and 14, 2015.. 


    Please Be Advised:

    • Signs, cones,